Dordikhola Hydropower Project begins power generation

August 29, Kathmandu: The Dordikhola Hydropower Project in Lamjung district has begun test production from Sunday.
The project with the capacity of 27 megawatt commenced test production after completing the entire construction works, Project Chief Munna Shakya said.
According to Shakya, the test production will continue for four to five days adding that commercial production of the power will begin once the test production was successful.
The total cost of the project is estimated to be around Rs 4.64 billion though it was expected to complete with an investment of Rs 4.23 billion.
Non-Resident Nepalis Association (NRNA) has invested 35.7 percent, IME Group has 34.3 percent and 30 percent of the public for the project development.