Kaligandaki Corridor transmission line completes

January 5, Myagdi: Infrastructure development of two substations and electricity transmission line of Kaligandaki Corridor Transmission line has been completed.
Chief of the project Chandan Kumar Ghosh informed that all the infrastructure development works of 220 to 132 KV Capacity transmission line had been completed.
He added that the project had now reached the phase of internal testing.